● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work
参考答案
立即搜索
您可能感兴趣的试题
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.