● 在开发的软件产品完成系统测试之后,作为最终产品应将其存入(62) ,等待交付用户或现场安装。
-
● 某软件开发项目计划设置如下基线:需求基线、设计基线、产品基线。在编码阶段,详细设计文件需要变更,以下叙述中,(63)是正确的。
-
● 某个配置项的版本由1.11变为1.12,按照配置版本号规则表明(64) 。
-
● 配置审计包括物理审计和功能审计,(65)属于功能审计的范畴。
-
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.
-
● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.